ARCHIVED: Completed project: IU UniCom (Unified Communications)

This content has been archived, and is no longer maintained by Indiana University. Information here may no longer be accurate, and links may no longer be available or reliable.

Primary UITS contact: Jennifer Van Horn

Completed: May 28, 2009

Description: This project involves the integration of the Nortel CS2100 PBX software and Microsoft Office Communications Server (OCS) 2007 software to provide a unified communications and collaboration platform to the desktop. This service is now available to all IU faculty, staff, and students.

Outcome: The project's goal is to improve productivity, creativity, and collaboration by implementing advanced communication tools in one platform on the desktop. It provides a platform to converge telephony, email, instant messaging, enhanced presence, audio and videoconferencing, and mobility.

Milestones and status:

The project began in May 2007. The project plan is as follows:

  • June 11, 2007: Procure hardware for OCS Server Completed
  • July 2007: Install servers and connect to network Completed
  • July 2007: Implement clustered SQL and SAN installation Completed
  • July 9, 2007: Configure server iLO boards Completed
  • July 2007: Upgrade SL100 PBX to the CS2100 hardware and software Completed
  • July 2007: Install HTTP Reverse Proxy Completed
  • August 2007: Install CS2100 upgrade for OCS Completed
  • September 2007: Install public release version of OCS 2007 Completed
  • October 4, 2007: CS2100 SE10 upgrade Completed
  • October 12, 2007: Begin integration of CS2100 and OCS 2007 95% completed
  • October 4 to November 29: SE10 OCS 2007 integration trial period
  • October 2007: Identify pre-pilot group Completed
  • October 2007: Identify pilot group Completed
  • October 2007: Install production OCS client for pre-pilot group users Completed
  • October 2007: Begin pre-pilot testing Ongoing
  • December 2007: Load OCS Service Release Completed
  • December 2007: Create communications and marketing plan Ongoing
  • December 2007: Create support model Draft plan in place
  • December 2007: Install the Communicator Web Access (CWA) server Completed
  • January 2008: Create client installation package through IUware Completed
  • January 16, 2008: LSP InfoShare UniCom Project Demonstration.
  • February 2008: Begin pilot group testing with partial group of UITS pilot users Completed
  • February 2008: Install external access servers Completed
  • March 2008: Add additional UITS and LSP users to the pilot group Completed
  • May 19, 2008: UniCom service moves to the production environment with limited campus availability
  • June 2008: Indiana University participates in a Microsoft Case Study as part of the Public Sector Partner Solution MarketPlace.
  • June 2008: University of Kentucky federates with IU
  • June 2008: Demos for Kelley School of Business Completed
  • July 2008: Texas Tech University federates with IU
  • July 16, 2008: IU presents the UniCom project at the ACUTA Annual Conference.
  • July 24, 2008: Demo for Council of CIOs
  • July 29, 2008: Demo for University Engineers
  • August 12, 2008: Reached a major milestone of having 1,000 OCS client accounts activated
  • August 2008: Demos for the School of Nursing, School of Medicine, and teaching and learning centers' Town Hall Meeting
  • August 2008: Prepare functional requirement for the integration of OCS with Oncourse
  • August 2008: Begin work to integrate OCS with the Tandberg videoconferencing units
  • September 2008: Participate in Gartner Group case study
  • September 10, 2008: Participate in Make IT Happen Day at IUB
  • September 11, 2008: Presentation at LSP Appreciation Event
  • September 12, 2008: Presentation at the IU Statewide IT Conference
  • September 23, 2008: Move service to full campus deployment
  • September 24, 2008: 1,421 OCS client accounts activated
  • September 25, 2008: Demo for School of Medicine LSPs
  • September 2008: Telecommunications coordinator InfoShares at IUB and IUPUI
  • October 2008: OCS client installed on all Student Technology Center computers
  • October 2008: Demos for School of Optometry and School of Journalism
  • October 20, 2008: Federated with Rose-Hulman
  • October 28, 2008: Participated in Make IT Happen Day at IUPUI
  • November 10, 2008: Gartner publishes "Case Study: Indiana University Deploys Unified Communications"
  • November 11, 2008: Participated in Make IT Happen Day at IU Southeast
  • December 2008: 1,934 OCS client accounts activated
  • December 2008: Postcard mailed to all deans, directors, and department heads at IUB and IUPUI to publicize UniCom service

Comment process: Send email to Jennifer Van Horn.

Benefits:

  • Simplicity: This project streamlines communications across a consistent client interface.
  • Unified access: Voice, video, IM, file sharing, email, calendar, and enhanced presence are available in one convenient desktop interface.
  • Ad hoc meetings: Save travel time and money with no need to schedule a conference room.

Primary client: Faculty, staff, and students

Client impact: Clients may continue using their existing phones or move to a fuller-featured voice-over-IP phone or OCS-optimized phone. They can also use OCS to integrate with Outlook for presence management and to initiate instant message chats, group chats, voice calls, or videoconferencing.

Project team:

  • Jennifer Van Horn, Project Manager
  • Matt Dixon, Infrastructure team leader
  • Rick Jackson, Infrastructure team member
  • Peter Uthuppuru, Infrastructure team member
  • Paul Clegg, Telephony team leader
  • Jerry Perkins, Telephony team member
  • Mark Spencer, Telephony team member
  • Michael Morgan, Telephony team member
  • Elizabeth Venstra, Communications team member
  • Chip Rondot, Communications team leader
  • Greg Moore, Communications team member
  • Chris England, LSP consultant
  • Jonny Sweeny, Security team member
  • Carol Rhodes, Training team leader
  • Dennis Gillespie, Support team leader
  • Barb Patrick, Support team member
  • Aimee Staggs, Support team member
  • Lori Pollock, Support team member
  • Drew Hostetler, Support team member
  • Chris Golden, Video consultant
  • Rick Watson, System Engineer, Nortel
  • Andy Cheezum, Account Manager, Nortel

Governance: Mike Lucas, Operations and Systems Director, Enterprise Infrastructure (Executive sponsor)